Connect with us

News

Despite spending Rs. 50 Crores in 19 years, HPSEB couldn’t complete Bokhtu-Pooh-Kaza–Losar power line

Published

on

Bokhtu-Pooh-Kaza–Losar

To fill vacancies in electricity Board Limited, as many as 3000 posts of the field staff would soon be filled and deputed in tribal and other areas, said the CM

SHIMLA-   The proposed 66 KV power transmission line from Bokhtu (Karcham Wangtu) to Kaza uptill Losar is not complete after 19 years despite expenditure of Rs. 50 Crores by Himachal Pradesh State Electricity Board (HPSEB). The 66-KV/22-KV lines were to be laid between Karcham to Kaza covering distance of over 150 km, which would have provided uninterrupted power supply to far-flung areas of Lahaul and Spiti and Kinnaur district.

The project was conceived way back in 1997 and it should have been completed till now. The department should have thought of laying underground cables, wherever feasible, to overcome the natural impediment.

However, in reply it was disclosed that the line from Bokhtu was made operational in 2005, but due to heavy snowfall in 2015, the wires were snapped at many places which were made operational and power restored in January 2016.

The board has assured that the 66 KV electric sub-station at Pooh would be set up soon as all formalities are complete. From Akpa to Pooh, 110 towers had been installed and the electric supply was now normal, claims the CM while presiding over the meeting of the State Tribal Advisory Council (TAC). From Pooh to Kaza 107 kilometers of transmission wire is proposed to be laid covering 107 kilometers but there were few sliding and glacier zones. The department proposes to install 206 electric poles leaving aside glacier and sliding zones which included the transmission line from Chango to Sumdo (13 Kms), Hurling to Poh (33 Kms), Sichling to Lingti (8 Kms), and Lidaang to kaza (12 kms). The survey, he said, is complete and estimates were being prepared and the detailed project report from Kaza to Losar was also ready.

Atargu-Mudh-Bhawa Road Progress

The slow pace of work on Atargu-Mudh-Bhawa road (106 Kms), which would shorten the distance of around 100 kilometers to Pin valley, is another matter of concern. A stretch of 33.5 Kms of road was completed from Kaza side and a portion of around 28 Kms falls in Pin Valley National Park Wildlife Sanctuary. He said the matter pertaining to forest clearance would be taken up in State Wild Life Board meeting and directed the forest department to pursue the matter with central empowered committee so that the road could be through giving much relief to inhabitants of Spiti.

Urni Dhank Tunnel Construction 

Discussions were also held regarding construction of tunnel at ‘Urni Dhank’, for a permanent solution to overcome the huge blockade. The two alternate bridges were recently opened for vehicular traffic and as far the issue regarding tunnel is concerned a consultant had been appointed and the report is awaited. Directions were issued to complete ongoing work on Leo by-pass road in Kinnaur district. Being border road it will also shorten the distance between Ka and Chango villages to approximately 17 Kilometers.

Kahdu Nallah to Sansari Nallah Road Widening

The Chief Minister said that improvement, resurfacing and widening of road from Kahdu Nallah to Sansari Nallah, bordering Jammu and Kashmir, in Pangi subdivision of district Chamba should be done systematically. At present the road is under GREF and as per GREF authorities, few kilometers of portion was outsourced and they can do only after permission from Ministry of Defence (MoD) for which they were pursuing the matter.

Mooling Bridge Construction Progress

The Chief Minister also directed to complete the work on Mooling Bridge by June 2017. It was also disclosed that a bailey bridge on Chandra River connecting North Portal of Rohtang Tunnel would be completed within a week. The bridge was constructed in 2006, near Telling village at Sissu in Lahaul and Spiti collapsed on July 29 2016 due to strong current of River Chandra and was on the material supply bridge to North Portal of Rohtang tunnel.

Deluxe Bus between Sangla and Delhi

Decision was taken to ply deluxe bus between Sangla and Delhi, and few local buses in Keylong Trilokinath and Udaipur. It was disclosed that 22 HRTC buses were being deployed in Tribal belts of the State to facilitate the people.

The Chief Minister also issued direction to take action against the contractor who had failed to complete the work of Girls Hostel (Eklavya Bhawan) at Nichar in Kinnaur which was in limbo for quite some time.

3000 Posts in Electricity Board

On the issue of vacancies in electricity Board Limited, the Chief Minister revealed that as many as 3000 posts of the field staff would soon be filled and deputed in tribal and other areas. It was also decided to open a IPH rest house at Udaipur instead at Rangwey.

In 2016-17, a provision of Rs 696 crore had been made under Plan and Rs 610 crore under Non-Plan for Tribal areas of the State for development activities.

Expenditure on Roads, Health, Irrigation & Public Health in tribal areas

The Chief Minister said that a sum of Rs 76 crore was being spent on roads, Rs 189 crore on health and Rs 55.44 crore on Irrigation and Public Health sector in tribal areas of the State, besides a sum of Rs 25 crore on Border Area Development Programme (BADP). In addition to this, Rs 20.76 crore had been distributed as relief to the people in Tribal areas due to losses suffered to their property due to natural disaster, he added.

Photo: Representational

 

News

Himachal Teen Survives 12-Minute Leopard Attack, Kills Predator in Self-Defense

Published

on

solan teen kills leopard

Solan—In a shocking incident on Monday, an 18-year-old youth, Pravesh, survived a vicious leopard attack in Sarli village of Arki subdivision. The teenager reportedly fought the leopard for nearly 12 minutes before breaking its jaw, killing the animal on the spot.

Quick Thinking Saved His Life

Pravesh told the media that he was walking from the fields to a nearby shop in the morning to fetch milk when the leopard, hidden in the crops, lunged at him. Noticing the leopard’s tail, he attempted to run but fell after a short distance. During the attack, he covered his neck with his hands to protect himself from fatal bites.

The teenager continued to struggle with the leopard, repeatedly attempting to put distance between himself and the predator. In a desperate move, he grabbed the leopard by its mouth, twisted its jaw, and broke it, killing the animal instantly. Pravesh sustained multiple injuries, including deep claw marks, and is currently receiving treatment at Arki Hospital. Police and forest department teams have launched an investigation into the incident.

Serious Allegations of HP Forest Department’s Negligence

One of Pravesh’s relatives accused the forest department of negligence, noting that similar attacks had occurred in the area previously.

Earlier, a leopard had attempted to attack a scooter rider, who managed to escape. The family said they had informed the forest department on March 6 about potential danger, but no concrete action was taken. Villagers waited for three hours for a forest team to arrive, but none came. When the Block Officer eventually visited, he reportedly told villagers to ensure their own safety. Requests for cages to capture the leopard were also denied, with officials asking for written complaints instead.

Continue Reading

News

Weather Forecast for Himachal Pradesh For the Next Two Weeks

Published

on

Himachal weather forecast August

SHIMLA | 7 August 2025 –The India Meteorological Department (IMD) has forecast light to moderate rainfall across Himachal Pradesh over the next two weeks, with isolated heavy to very heavy showers likely over the low hills, plains, and adjoining mid-hill regions. While the ongoing monsoon remains vital for agriculture, it also brings an elevated risk of localized flooding and landslides.

Week of August 8–14

Maximum temperatures will range from 22°C to 34°C, depending on elevation—22°C to 28°C in high hills, 26°C to 30°C in mid-hills, and up to 34°C in lower regions. Minimum temperatures are expected to remain near normal, between 12°C and 24°C. Cooler conditions may persist in districts like Kullu and Lahaul-Spiti.

Week of August 15–21

Similar rainfall patterns are expected to continue, with scattered heavy rain episodes. Temperature trends will remain stable, though slightly below-normal maximum temperatures are likely in parts of Lahaul-Spiti, Mandi, Kangra, and Kullu districts.

Outlook for Late August

Rainfall is expected to remain broadly normal, with region-specific variations. Districts such as Kinnaur, Shimla, and Sirmaur may see below-normal precipitation, while Una, Kangra, Hamirpur, Bilaspur, and Solan are likely to receive above-average rainfall. Both maximum and minimum temperatures are forecast to stay close to seasonal norms.

Officials at the Meteorological Centre in Shimla have urged residents and local authorities to remain alert for sudden heavy downpours, which could disrupt road connectivity and trigger landslides—especially along vulnerable hillside routes. Past monsoon episodes have blocked key highways, including routes between Mandi and Kullu and near Banjar, underscoring the ongoing challenges in the region.

This advisory comes as Himachal Pradesh continues to face the dual pressures of sustaining its agriculture-dependent economy while managing the life and infrastructure risks posed by an active monsoon. Continued vigilance and preparedness remain crucial.

Continue Reading

News

Monsoon 2025: Himachal Pradesh Suffers 199 Casualties, Over ₹1,905.50 Cr in Damages

Published

on

Himachal-Pradesh-Monsoon-report-2025

SHIMLA | 7 August 2025 –Himachal Pradesh continues to deal with the impacts of the 2025 monsoon season, reporting extensive property damage, loss of lives, and widespread disruptions across the state. According to the official reports from the State Emergency Operations Centre (SEOC), the Department of Revenue, and the India Meteorological Department, from June 20 to August 6, 2025, heavy monsoon rains caused significant damage across multiple districts:

  • Casualties: 199 deaths due to landslides, flash floods, cloudbursts, drowning, lightning, electrocution, and accidents; 304 injuries reported.
  • Property Loss: Extensive damage to houses (both pucca and kaccha), shops, factories, labor sheds, animal shelters, and substantial crop losses in agriculture and horticulture.
  •  Public Infrastructure: Over ₹1,900 crore in damages to roads (including PWD), power supply, health, education, fisheries, rural and urban development, and animal husbandry.

Most affected districts include Mandi, Kangra, and Hamirpur, with severe crop and infrastructure losses.

Monsoon damages in himachal pradesh

 

Additionally, 91 deaths occurred due to monsoon-related road accidents.

Public Utilities and Infrastructure Disruptions

The SEOC report dated August 7, 2025, highlights ongoing disruptions:

  • Roads Blocked: About 493 major roads and 3 national highways (NH-305, NH-21, NH-05) remain blocked by landslides and floods.
  • Power Supply: Disruption of 1,120 distribution transformers (DTRs).
  •  Water Supply: 245 water schemes affected, threatening access to potable water for communities.

Key blockages include NH-21 between Mandi and Kullu and NH-305 near Banjar and Jhed.

Weather Forecast and Warnings

The India Meteorological Department’s forecast valid from August 7, 2025, includes:

  •  Isolated heavy rainfall expected throughout the week.
  •  Thunderstorms and lightning predicted in isolated areas.
  •  Minimum temperatures near normal or slightly below.
  •  Maximum temperatures showing a moderate increase.

The public is urged to remain vigilant due to the risks of further landslides and flash floods.

Himachal Pradesh remains vulnerable as the monsoon season continues, with thousands affected by damage, displacement, and disruption of essential services. Authorities are continuing with rescue and recovery operations and are urging residents to stay alert to the ongoing adverse weather. This situation highlights the pressing need for enhanced infrastructure and disaster management strategies to mitigate monsoon-related risks.

Continue Reading

Trending